As of writing, water main work in Winchester Village is substantially complete. Thank you for your patience! The contractor is installing curbs, sidewalks,...
The Morrish Road project is fully open to traffic and substantially complete. This project should be behind us very shortly. The city inspected the project...
Bids will be opened on June 1 for Miller Road (Morrish to Seymour), with approval of a contractor expected on June 12. The DDA has recommended approval...
Miller Road resurfacing is underway. This will also include repair of select drainage structures, joint repair, and a significant amount of curb replacement...
Miller Road rehabilitation continues. The project includes repair of select drainage structures, joint repair, and a significant amount of curb replacement...
Bids have been approved for the next installment of street and water main work in the city. The contractor indicates a desire to commence in mid-winter...
In addtion to the udpates below, Winchester Woods is scheduled to commence this year. Note that this project and the prime contractor are not affiliated...