January 2024 City Street Update

 
Forestry and sidewalk demolition
Water main installation and service line attachment
Street demolition and new storm sewer installation
Curbs, sidewalk, and apron installation
Road paving
 
Note that there will be 2-3 crews onsite for the duration of the project, with different geographies in the project area subject to different work items at various times. In addition, the contractor will be completing some areas much sooner than others. For example, some areas may experience final road surfacing as early as July, while others may not have their road surface completed until October, when the project is expected to be substantially complete.
 
Residents can expect to receive door hangers indicating water service interruptions, driveway access issues, and related updates. The standard construction letter that includes general project information and contacts can be viewed here.
 
In addition, the city is expected to award bids for the Winchester Woods street rehabilitation in February, with this project also expected to conclude in the fall of 2024. For details on these projects, see the prior updates below.