Bids have been approved for the next installment of street and water main work in the city. The contractor indicates a desire to commence in mid-winter and conclude all work in 2024. The scope of work includes:
Norbury (Road reconstruction and water main replacement)
Durwood (Road reconstruction and water main replacement)
Greenleaf (Road reconstruction and water main replacement)
Whitney (Road reconstruction and water main replacement)
Winshall (Road reconstruction and water main replacement)
Seymour (limited water main replacement)
Reconstruction includes new storm systems, road base, asphalt, curb, sidewalks, drive approaches, and forestry.
Note that Don Shenk is not included in this phase because the water main for this street is relatively new. Street reconstruction will follow this phase, which is largely related to required water main replacement.
The city also acquired a $250,000 MDOT Category B grant, enabling rehabiltiatoin of streets in Winchester Woods. This project is expected to be bid in early 2024 and commence in 2024. All improved streets in Winchester Woods are included.