September 2023 Street Update
August 2023 Street Update
May 2023 Street Update
January 2023 Street Update
The Morrish Road project is fully open to traffic and substantially complete. This project should be behind us very shortly. The city inspected the project with the engineer to see if it is ready to close out. Staff has concerns about some apparent reflective cracking. While cracking over joints is not uncommon for rehabilitation projects, there is a substantial amount that may be cause for concern. This is most notable around Fortino and the storage units on Morrish.
We have an agreement with the MDOT for the Miller Road buyout, which might make funds available for 2023. With that said, we are looking to bid in the late winter and need to finalize preliminary engineering. OHM is working on final engineering, and we hope to bid soon.
The federal award for this project has been increased from $1,054,959 to $1,249,499. At 90%, our share is up to $1,124,549 from $949,463. This money will be much less restricted road money, which should enable us to complete the necessary resurfacing, joint work, curb, and drainage, without needing to focus on other MDOT requirements. Note that cost increases and the continuing need to pay Davis Bacon wages (prevailing wages) may still dig into local reserves.
If bids are low, funds can be spent to expand the project scope as we see fit. There is no shortage of deferred maintenance on other major streets (south Morrish, concrete portions of Miller, and even parts of east Miller and Elms). Another options is some striping or lane change configurations downtown, should the city wish to explore on-street parking on Miller from Morrish to Hayes.
With that said, OHM has modeled an option for this segment with on street parking. Doing so will certainly have the mixed impact of slowing traffic, as well as the obvious increase to parking spaces, an increased buffer for sidewalk uses. The study was in the November 14, 2022 council packet. We will need to decide if we wish to pursue this prior to having the roadwork commence.
The DDA discussed this matter at their meeting on November and December meetings. There was support and opposition, with no recommendation.
All other street work for 2022 is substantially complete. Road paint has been completed on Bristol, Seymour, and Hill. However, there are still some missing stop bars and specialty markings (approved at the September 12 meeting). Note that Seymour now has a double yellow line centered on the street, with edge lines included to provide for shoulders on both sides. The lane width is at 10.5’. This should result in traffic calming and provide a safer space for bikers.OHM is preparing preliminary engineering for the remainder of Winchester Village and Winchester Woods. This is a very large scope of work. As observed with the recent streets in the Village, the water main that is in place is 70-year-old cast iron, with failing joints. As such, it is imperative to replace water main for those streets that have original pipe (note that this excludes Don Shenk, which has ~20 year old water main, with a corresponding top coat of asphalt).
In order to tackle such a large scope of water main, we intend to bond with the USDA for another phase. This means that the water main work must be completed in two construction seasons. The removal of the street and existing main further necessitates that the streets be completed in the same timeline. As such, a street bond is prudent.
We are currently finalizing the USDA borrowing process and should be ready to bid the water main and streets this winter. The USDA and street bond processes will be conducted concurrently, but they are separate and distinct. Note that delivery times for ductile iron are extensive, from 8 to 12 months. This could prevent any meaningful work form occuring in 2023.
Mid-July Street Update
July Street Update
May 2022 Street Update
April 2022 Street Update
2022 is going to be very busy in Swartz Creek. Miller Road water main is finishing up now, but replacement curb work and restoration will continue into late spring. Morrish Road rehabilitation is underway. This is a resurfacing project from Bristol to Miller that was selected for funding by the Genesee County Traffic Improvement Program. Some folks have asked, "why this road." The answer lies in the old adage that "an ounce of prevention is worth a pound of cure." This street has surface deterioration, but a strong base. As such, the road received federal rehabilitation funds to address the surface prior to major defects. This road project will take about ten weeks, with the south bound lane closed for phase one and the north bound land closed for phase two. This is the best solution available given practical consideration, design requirements, and MDOT traffic control guidance. The project will also include a left turn lane on Paul Fortino, onto Morrish.
To address additional street deterioration, several local street projects will also be completed by this fall. These projects will be surface rehabilitation, but they will provide timely maintenance to protect road bases and improve the surface. The projects should also progress much faster. Areas approved for resurfacing include: Hill Road (Seymour to city limits), Seymour Road (Miller to city limits) and Bristol Road (Elms to city limits, including base repair at Jennie Lane). In addition, we expect to have surface restoration for the Library/Senior Center/Civic area parking lot. Notice will go out to those organizations to avoid service disruptions.
Miller Road, from Morrish to Seymour, has been selected for TIP federal funding. The year of construction has not been determined but is likely to be 2024.
Lastly, even bigger plans are in the works for 2023-2024. A USDA phase II investment will enable water main replacement for those streets in Winchester Village that are still on original cast iron mains. Concurrent with this, we will be reconstructing those streets in the same manner as the recent projects. Engineering is already underway, with bids to be solicited later this year to finish up this work. Doing so will bring us very close to substantial completion of the Winchester Village infrastructure investment. Note that we are already hearing of major delays (months, perhaps a year) on such supplies. We are not expecting delays for a 2023 commencement yet, but such supply issues may become a reality. We expect to be resurfacing much of Winchester Woods at this time as well.
October 2021 Street Update
June 2021 Street Update
July Street Update
May 2022 Street Update
April 2022 Street Update
2022 is going to be very busy in Swartz Creek. Miller Road water main is finishing up now, but replacement curb work and restoration will continue into late spring. Morrish Road rehabilitation is underway. This is a resurfacing project from Bristol to Miller that was selected for funding by the Genesee County Traffic Improvement Program. Some folks have asked, "why this road." The answer lies in the old adage that "an ounce of prevention is worth a pound of cure." This street has surface deterioration, but a strong base. As such, the road received federal rehabilitation funds to address the surface prior to major defects. This road project will take about ten weeks, with the south bound lane closed for phase one and the north bound land closed for phase two. This is the best solution available given practical consideration, design requirements, and MDOT traffic control guidance. The project will also include a left turn lane on Paul Fortino, onto Morrish.
To address additional street deterioration, several local street projects will also be completed by this fall. These projects will be surface rehabilitation, but they will provide timely maintenance to protect road bases and improve the surface. The projects should also progress much faster. Areas approved for resurfacing include: Hill Road (Seymour to city limits), Seymour Road (Miller to city limits) and Bristol Road (Elms to city limits, including base repair at Jennie Lane). In addition, we expect to have surface restoration for the Library/Senior Center/Civic area parking lot. Notice will go out to those organizations to avoid service disruptions.
Miller Road, from Morrish to Seymour, has been selected for TIP federal funding. The year of construction has not been determined but is likely to be 2024.
Lastly, even bigger plans are in the works for 2023-2024. A USDA phase II investment will enable water main replacement for those streets in Winchester Village that are still on original cast iron mains. Concurrent with this, we will be reconstructing those streets in the same manner as the recent projects. Engineering is already underway, with bids to be solicited later this year to finish up this work. Doing so will bring us very close to substantial completion of the Winchester Village infrastructure investment. Note that we are already hearing of major delays (months, perhaps a year) on such supplies. We are not expecting delays for a 2023 commencement yet, but such supply issues may become a reality. We expect to be resurfacing much of Winchester Woods at this time as well.
October 2021 Street Update
June 2021 Street Update
February Street Update
November Street Update
May Street Update
April Street Update
March 2020 Street Update
February Street Update
November Street Update
May Street Update
April Street Update
March 2020 Street Update
June 2019 Street Update
May 2019 Street Update
April Street Update
June 2019 Street Update
May 2019 Street Update
March 2019 Street Update
May Street Updates
April Street Update
March Street Update
2018 will not be as busy as 2017. However, those residents on Daval will probably wish they were somewhere else by mid-summer.
Reconstruction of Daval is the sole reconstruction project for this year. Any rehabilitiation or maintenance projects will be announced in future reports.
The Daval project, though smaller in scope, will resemble the reconstruction efforts from last year and include the following:
- Replacement of Consumers Energy gas services by Consumers Energy and/or their private contractors (March)
- Removal of most street right-of-way trees (March)
- Replacement of all water main, water services, and storm drain features (April-July)
- Removal and replacment of the street, curb, gutter, sidewalk, street trees, select decorative lamps/signs (July-September)
Waste and recycling is still planned for curbside pickup.
Driveway interuptions will occur as necessary to trench water main, remove/replace curb/sidewalk/drive approaches. The estimated interuptions that are expected to deny access are overnight is set at 6-8 days. The contract will inform you in advance of these interuptions and indicate where you should be able to park.
See prior reports (below) to view the FAQ, which covers forestry, timelines, and other common matters.
Common contacts are:
City Hall (general questions): 810.635.4464
Joe Pacek (construction issues): 810.869.5108
Contractor (for private work add-ons): 810.487.1560
November Street Update
October Street Updates
Trick or Treating in the city will officially be recognized on October 31st from 6:00 p.m. until 8:00 p.m. Treat or Treating will NOT be permitted in the street reconstructions zones of Worchester, Chesterfield, and Winston Drives for safety reasons!
September Street Update
August Update!
Work on Abbey Lane and Ingalls Street is underway, with concrete work and milling of asphalt occuring the week of the 14th. The plan is to have substantial completion before school starts. There is more rain that is typical for August in the forecast that we hope we can work through.
We are still unable to pin down the contractor that was approved to apply the cape seal to the streets slated for preventative maintanance. This work was to begin on July 25th and has still not commenced. Once the contractor begins, all work should be completed within two or three business days and cause minimal disruption.
Reconstruction efforts will be in full swing soon for Chesterfield, Winston, and Worchester. This process will include total street, curb, drive approach, and sidewalk removal and replacement. There will be pronounced dust, noise, and access issues. Please work with our contractor to complete this as painlessly as possible. If you are experiencing issues that appear to be outside the expected scope of a reconstruction, please contact the city office at 810.635.4464.
March Street Update
2018 will not be as busy as 2017. However, those residents on Daval will probably wish they were somewhere else by mid-summer.
Reconstruction of Daval is the sole reconstruction project for this year. Any rehabilitiation or maintenance projects will be announced in future reports.
The Daval project, though smaller in scope, will resemble the reconstruction efforts from last year and include the following:
- Replacement of Consumers Energy gas services by Consumers Energy and/or their private contractors (March)
- Removal of most street right-of-way trees (March)
- Replacement of all water main, water services, and storm drain features (April-July)
- Removal and replacment of the street, curb, gutter, sidewalk, street trees, select decorative lamps/signs (July-September)
Waste and recycling is still planned for curbside pickup.
Driveway interuptions will occur as necessary to trench water main, remove/replace curb/sidewalk/drive approaches. The estimated interuptions that are expected to deny access are overnight is set at 6-8 days. The contract will inform you in advance of these interuptions and indicate where you should be able to park.
See prior reports (below) to view the FAQ, which covers forestry, timelines, and other common matters.
Common contacts are:
City Hall (general questions): 810.635.4464
Joe Pacek (construction issues): 810.869.5108
Contractor (for private work add-ons): 810.487.1560
November Street Update
October Street Updates
Trick or Treating in the city will officially be recognized on October 31st from 6:00 p.m. until 8:00 p.m. Treat or Treating will NOT be permitted in the street reconstructions zones of Worchester, Chesterfield, and Winston Drives for safety reasons!
September Street Update
August Update!
Work on Abbey Lane and Ingalls Street is underway, with concrete work and milling of asphalt occuring the week of the 14th. The plan is to have substantial completion before school starts. There is more rain that is typical for August in the forecast that we hope we can work through.
We are still unable to pin down the contractor that was approved to apply the cape seal to the streets slated for preventative maintanance. This work was to begin on July 25th and has still not commenced. Once the contractor begins, all work should be completed within two or three business days and cause minimal disruption.
Reconstruction efforts will be in full swing soon for Chesterfield, Winston, and Worchester. This process will include total street, curb, drive approach, and sidewalk removal and replacement. There will be pronounced dust, noise, and access issues. Please work with our contractor to complete this as painlessly as possible. If you are experiencing issues that appear to be outside the expected scope of a reconstruction, please contact the city office at 810.635.4464.
Water Outage Wednesday, Aug. 2nd
Water will be off tomorrow 8/2/17 approximately 8:30 am until around 3:00 pm on the following streets:
Seymour from Young to Miller
Chesterfield from Daval to Eaton & Natalie
July Street Update Supplement
Preventative maintenance on streets slated for the slurry seal is expected to occur between July 25th and Juily 28th.
Ingalls Street and Abbey Lane are slated for resurfacing. This will include some curb replacement, milling of the top asphalt layer, and replacement with new asphalt. Ingalls Street, between School and Fairchild is proposed for narrowing, which will include a new curb and sidewalk installation on the north side. This change will eliminate onstreet parking, increase pedestrian safety, and lower the design speed. This project is expected to be substantially complete in mid-September.
July Street Update
The city will be completing a ‘cape seal’ project on the following streets:
1st Street
2nd Street
3rd Street
Brady: Ingalls to Miller
Jennie Lane
Ford: Ingalls to Miller
Hayes: Ingalls to Miller
Mclain Street
Wade Street
The contractor intends to begin July 25th and complete all work by July 27th. The treatment will include chip seal application with a top coat of asphalt slurry. For those in the downtown area, this surface treatment will resemble the maintenance that occurred approximately eight years ago. This form of maintenance has an expected life of 5-10 years.
The application of this surface treatment will close the streets to through traffic and will limit drive access during application for limited periods of time.
City Streets Updates - June 2017
Reconstruction is progressing well as we approach summer!
Forestry activities are complete.
Worchester – Water main has been installed, pressure tested, chlorinated and bacterial analysis has been completed. Service installation is expected to begin on June 13.
Chesterfield – Water main has been installed, pressure tested and chlorinated. Samples were taken on June 12.
Winston – Water main installation is underway and should be complete by June 14.
Storm Sewer - Survey was out Friday and today staking the new storm sewer on Worchester, Chesterfield. The contractor anticipates starting this work on or before June 19.
Preservation work on select downtown streets is expected to occur in late June. The disruption should be minimal.
May 2017 Update
Forestry is substantially complete in the reconstruction area. Water main is to be delivered beginning May 12, with excavation activities expected to begin on or soon after May 15.
Staging for construction is to take place ihn Winshall Park, near Whitney Court. Equipment and materials will be here throughout the duration of the project.
Waste and recycling is still planned for curbside pickup.
Driveway interuptions will occur as necessary to trench water main, remove/replace curb/sidewalk/drive approaches. The estimated interuptions that are expected to deny access are overnight is set at 6-8 days. The contract will inform you in advance of these interuptions and indicate where you should be able to park.
Contact city hall with questions at 810.635.4464.
Water Outage Wednesday, Aug. 2nd
Water will be off tomorrow 8/2/17 approximately 8:30 am until around 3:00 pm on the following streets:
Seymour from Young to Miller
Chesterfield from Daval to Eaton & Natalie
July Street Update Supplement
Preventative maintenance on streets slated for the slurry seal is expected to occur between July 25th and Juily 28th.
Ingalls Street and Abbey Lane are slated for resurfacing. This will include some curb replacement, milling of the top asphalt layer, and replacement with new asphalt. Ingalls Street, between School and Fairchild is proposed for narrowing, which will include a new curb and sidewalk installation on the north side. This change will eliminate onstreet parking, increase pedestrian safety, and lower the design speed. This project is expected to be substantially complete in mid-September.
July Street Update
The city will be completing a ‘cape seal’ project on the following streets:
1st Street
2nd Street
3rd Street
Brady: Ingalls to Miller
Jennie Lane
Ford: Ingalls to Miller
Hayes: Ingalls to Miller
Mclain Street
Wade Street
The contractor intends to begin July 25th and complete all work by July 27th. The treatment will include chip seal application with a top coat of asphalt slurry. For those in the downtown area, this surface treatment will resemble the maintenance that occurred approximately eight years ago. This form of maintenance has an expected life of 5-10 years.
The application of this surface treatment will close the streets to through traffic and will limit drive access during application for limited periods of time.
City Streets Updates - June 2017
Reconstruction is progressing well as we approach summer!
Forestry activities are complete.
Worchester – Water main has been installed, pressure tested, chlorinated and bacterial analysis has been completed. Service installation is expected to begin on June 13.
Chesterfield – Water main has been installed, pressure tested and chlorinated. Samples were taken on June 12.
Winston – Water main installation is underway and should be complete by June 14.
Storm Sewer - Survey was out Friday and today staking the new storm sewer on Worchester, Chesterfield. The contractor anticipates starting this work on or before June 19.
Preservation work on select downtown streets is expected to occur in late June. The disruption should be minimal.
May 2017 Update
Forestry is substantially complete in the reconstruction area. Water main is to be delivered beginning May 12, with excavation activities expected to begin on or soon after May 15.
Staging for construction is to take place ihn Winshall Park, near Whitney Court. Equipment and materials will be here throughout the duration of the project.
Waste and recycling is still planned for curbside pickup.
Driveway interuptions will occur as necessary to trench water main, remove/replace curb/sidewalk/drive approaches. The estimated interuptions that are expected to deny access are overnight is set at 6-8 days. The contract will inform you in advance of these interuptions and indicate where you should be able to park.
Contact city hall with questions at 810.635.4464.
City Streets Updates - March 2017
The pre-construction meeting for the reconstruction and rehabilitation projects has been held. We are still awaiting final details regarding waste collection options during construction and the final forestry plan. For now, it appears that waste collection will be at the curb for most of the project. The revised plans also call for replacement 5' sidewalk on both sides of Chesterfield, Worchester, and Winston.
Expect the gas line replacement to end at the beginning of April, followed by tree removal. Watermain replacement will then commence in phases, with street construction to occur in late summer/early fall. Check out the proposed construction schedule here.
Preventative maintenance bids have been approved for seal coating for about half of the downtown streets, including First, Second, Third, Wade, Brady (north of Ingalls), McLain (north of Ingalls), Ford, Hayes, as well as Jennie Lane in Ottoburn Heights. This project will create a lessor distrubance and require less time than the rehabilitation and reconstruction projects. A time has not yet been set for commencement.
City Streets Updates - February 2017
Street reconstruction and rehabilitation projects for 2017 have been approved and are in the pre-construction planning phase. Streets slated for reconstruction this year include:
Chesterfield (Seymour-Winston)
Winston
Worchester
The reconstruction projects will include complete removal and replacement of the road and curb, installation of new water main on the same side as the existing watermain, new driveway approaches, replacement sidewalk on the water main side, replacement of most trees on the water main side, and replacement of some trees on the non-water main side.
The general timeline will include replacement of the gas lines and services by Consumers Energy in March, water main work from April - June, and road replacement from June - November. This project will be messy and a horrible inconvenience! There will be interruptions in access, water service, and waste collection. The city and contractor will attempt to keep folks informed of these project occurrences via the city's webpage, Facebook, door hangers, the newsletter, and job site bulletin boards.
If you are directly impacted, expect to have waste services halted this summer. A garbage, yard waste, and recycling drop off point is planned for the center parking lot of Winshall Park.
In addition, there are streets slated for rehabilitation. These include:
Abbey Lane (new asphalt with some curb replacement)
Ingalls (new asphalt with some curb replacement, as well as a narrowing and sidewalk addition between Fairchild and School)
Lastly, many downtown streets are slated for a seal coat as a preventative maintenance feature. These bids have not yet been approved.
City Streets Updates - October 2016
Overband crack sealant is being applied to many miles of major and local streets, beginning October 12, 2016. This will create a bumpy ride for a few weeks, but it should settle in nicely by the time winter weather rolls in. Please be mindful of construction workers! The city has also contracted with a company to stripe the impacted roads so that we have visible markings for those long, dark winter commutes.
Concerning traffic circles and other features, there are no plans to include these in the upcoming street reconstruction projects (see the link for upcoming repairs and maintenance). However, pedestrian medians (islands) may be considered after bids are received in the spring. Please note that those streets slated for reconstruction are also proposed to have water main replaced. This means that the side with the existing water main shall be excavated, with all trees, sidewalk, and driveway approaches removed. This work is expected to be prolonged, beginning in April and ending in November. It will be unpleasant, with interruptions to access, waste collection, and water pressure. Please pardon the dust. Contact city hall with questions at 810.635.4464.
City Streets Updates
This page will be used to keep you up to date on the latest road construction projects in the City of Swartz Creek over the next many years to come.
City Streets Updates - March 2017
The pre-construction meeting for the reconstruction and rehabilitation projects has been held. We are still awaiting final details regarding waste collection options during construction and the final forestry plan. For now, it appears that waste collection will be at the curb for most of the project. The revised plans also call for replacement 5' sidewalk on both sides of Chesterfield, Worchester, and Winston.
Expect the gas line replacement to end at the beginning of April, followed by tree removal. Watermain replacement will then commence in phases, with street construction to occur in late summer/early fall. Check out the proposed construction schedule here.
Preventative maintenance bids have been approved for seal coating for about half of the downtown streets, including First, Second, Third, Wade, Brady (north of Ingalls), McLain (north of Ingalls), Ford, Hayes, as well as Jennie Lane in Ottoburn Heights. This project will create a lessor distrubance and require less time than the rehabilitation and reconstruction projects. A time has not yet been set for commencement.
City Streets Updates - February 2017
Street reconstruction and rehabilitation projects for 2017 have been approved and are in the pre-construction planning phase. Streets slated for reconstruction this year include:
Chesterfield (Seymour-Winston)
Winston
Worchester
The reconstruction projects will include complete removal and replacement of the road and curb, installation of new water main on the same side as the existing watermain, new driveway approaches, replacement sidewalk on the water main side, replacement of most trees on the water main side, and replacement of some trees on the non-water main side.
The general timeline will include replacement of the gas lines and services by Consumers Energy in March, water main work from April - June, and road replacement from June - November. This project will be messy and a horrible inconvenience! There will be interruptions in access, water service, and waste collection. The city and contractor will attempt to keep folks informed of these project occurrences via the city's webpage, Facebook, door hangers, the newsletter, and job site bulletin boards.
If you are directly impacted, expect to have waste services halted this summer. A garbage, yard waste, and recycling drop off point is planned for the center parking lot of Winshall Park.
In addition, there are streets slated for rehabilitation. These include:
Abbey Lane (new asphalt with some curb replacement)
Ingalls (new asphalt with some curb replacement, as well as a narrowing and sidewalk addition between Fairchild and School)
Lastly, many downtown streets are slated for a seal coat as a preventative maintenance feature. These bids have not yet been approved.
City Streets Updates - Information
City Streets Updates - October 2016
Overband crack sealant is being applied to many miles of major and local streets, beginning October 12, 2016. This will create a bumpy ride for a few weeks, but it should settle in nicely by the time winter weather rolls in. Please be mindful of construction workers! The city has also contracted with a company to stripe the impacted roads so that we have visible markings for those long, dark winter commutes.
Concerning traffic circles and other features, there are no plans to include these in the upcoming street reconstruction projects (see the link for upcoming repairs and maintenance). However, pedestrian medians (islands) may be considered after bids are received in the spring. Please note that those streets slated for reconstruction are also proposed to have water main replaced. This means that the side with the existing water main shall be excavated, with all trees, sidewalk, and driveway approaches removed. This work is expected to be prolonged, beginning in April and ending in November. It will be unpleasant, with interruptions to access, waste collection, and water pressure. Please pardon the dust. Contact city hall with questions at 810.635.4464.
City Streets Updates
This page will be used to keep you up to date on the latest road construction projects in the City of Swartz Creek over the next many years to come.