January 2023 Street Update

The Morrish Road project is fully open to traffic and substantially complete. This project should be behind us very shortly. The city inspected the project with the engineer to see if it is ready to close out. Staff has concerns about some apparent reflective cracking. While cracking over joints is not uncommon for rehabilitation projects, there is a substantial amount that may be cause for concern. This is most notable around Fortino and the storage units on Morrish.

We have an agreement with the MDOT for the Miller Road buyout, which might make funds available for 2023. With that said, we are looking to bid in the late winter and need to finalize preliminary engineering. OHM is working on final engineering, and we hope to bid soon.

The federal award for this project has been increased from $1,054,959 to $1,249,499. At 90%, our share is up to $1,124,549 from $949,463. This money will be much less restricted road money, which should enable us to complete the necessary resurfacing, joint work, curb, and drainage, without needing to focus on other MDOT requirements. Note that cost increases and the continuing need to pay Davis Bacon wages (prevailing wages) may still dig into local reserves.

If bids are low, funds can be spent to expand the project scope as we see fit. There is no shortage of deferred maintenance on other major streets (south Morrish, concrete portions of Miller, and even parts of east Miller and Elms). Another options is some striping or lane change configurations downtown, should the city wish to explore on-street parking on Miller from Morrish to Hayes.

With that said, OHM has modeled an option for this segment with on street parking. Doing so will certainly have the mixed impact of slowing traffic, as well as the obvious increase to parking spaces, an increased buffer for sidewalk uses. The study was in the November 14, 2022 council packet. We will need to decide if we wish to pursue this prior to having the roadwork commence.

The DDA discussed this matter at their meeting on November and December meetings.  There was support and opposition, with no recommendation.

All other street work for 2022 is substantially complete. Road paint has been completed on Bristol, Seymour, and Hill. However, there are still some missing stop bars and specialty markings (approved at the September 12 meeting). Note that Seymour now has a double yellow line centered on the street, with edge lines included to provide for shoulders on both sides. The lane width is at 10.5’. This should result in traffic calming and provide a safer space for bikers.

OHM is preparing preliminary engineering for the remainder of Winchester Village and Winchester Woods. This is a very large scope of work. As observed with the recent streets in the Village, the water main that is in place is 70-year-old cast iron, with failing joints. As such, it is imperative to replace water main for those streets that have original pipe (note that this excludes Don Shenk, which has ~20 year old water main, with a corresponding top coat of asphalt).

In order to tackle such a large scope of water main, we intend to bond with the USDA for another phase. This means that the water main work must be completed in two construction seasons. The removal of the street and existing main further necessitates that the streets be completed in the same timeline. As such, a street bond is prudent.

We are currently finalizing the USDA borrowing process and should be ready to bid the water main and streets this winter. The USDA and street bond processes will be conducted concurrently, but they are separate and distinct. Note that delivery times for ductile iron are extensive, from 8 to 12 months. This could prevent any meaningful work form occuring in 2023.