creek road work sign

City Street Information Downloads

November Street Update

The 2020 portions of Winston, Oakview, Chelmsford, and Oxford are substantially complete! Note that restoration may continue in the spring. Decorative lighting and signs are still in the works. If you have issues with tree or sign placement, please contact the city offices. Note that the parking on Oakview has been flipped from the east side to the west side to align opposite the water main and hydrants.
 
Projects for 2021 will include:
 
Chelmsford from Daval to Seymour
Oakview from Daval to Seymour
 
Improvements will include new water main; removal and replacement of the street, sidewalks, curbs; forestery; limited drainage work; lighting improvements; decorative signs.