March Street Update
2018 will not be as busy as 2017. However, those residents on Daval will probably wish they were somewhere else by mid-summer.
Reconstruction of Daval is the sole reconstruction project for this year. Any rehabilitiation or maintenance projects will be announced in future reports.
The Daval project, though smaller in scope, will resemble the reconstruction efforts from last year and include the following:
- Replacement of Consumers Energy gas services by Consumers Energy and/or their private contractors (March)
- Removal of most street right-of-way trees (March)
- Replacement of all water main, water services, and storm drain features (April-July)
- Removal and replacment of the street, curb, gutter, sidewalk, street trees, select decorative lamps/signs (July-September)
Waste and recycling is still planned for curbside pickup.
Driveway interuptions will occur as necessary to trench water main, remove/replace curb/sidewalk/drive approaches. The estimated interuptions that are expected to deny access are overnight is set at 6-8 days. The contract will inform you in advance of these interuptions and indicate where you should be able to park.
See prior reports (below) to view the FAQ, which covers forestry, timelines, and other common matters.
Common contacts are:
City Hall (general questions): 810.635.4464
Joe Pacek (construction issues): 810.869.5108
Contractor (for private work add-ons): 810.487.1560
November Street Update
October Street Updates
Trick or Treating in the city will officially be recognized on October 31st from 6:00 p.m. until 8:00 p.m. Treat or Treating will NOT be permitted in the street reconstructions zones of Worchester, Chesterfield, and Winston Drives for safety reasons!
September Street Update
August Update!
Work on Abbey Lane and Ingalls Street is underway, with concrete work and milling of asphalt occuring the week of the 14th. The plan is to have substantial completion before school starts. There is more rain that is typical for August in the forecast that we hope we can work through.
We are still unable to pin down the contractor that was approved to apply the cape seal to the streets slated for preventative maintanance. This work was to begin on July 25th and has still not commenced. Once the contractor begins, all work should be completed within two or three business days and cause minimal disruption.
Reconstruction efforts will be in full swing soon for Chesterfield, Winston, and Worchester. This process will include total street, curb, drive approach, and sidewalk removal and replacement. There will be pronounced dust, noise, and access issues. Please work with our contractor to complete this as painlessly as possible. If you are experiencing issues that appear to be outside the expected scope of a reconstruction, please contact the city office at 810.635.4464.